CASE STUDIES

Malabar Rail Cutting Remediation

Hydromulching |
EnviroLoc Hydromulching BFM, EnviroSoil |
Rail

Background

Following geotechnical inspections of the earthwork cuttings and embankments along the Antiene Spur (Drayton – Malabar Branch Line), Erizon was engaged by Lycopodium’s rail engineering team to address erosion and poor vegetation cover. The maintenance closure of the Drayton to Malabar line in late May provided an opportunity for safe access and application of the remediation solution.

Project Overview

Erizon conducted a site visit to assess physical and environmental conditions, collect soil samples, and perform a drone survey. The soil samples underwent comprehensive agricultural testing in a laboratory. Analysis by Erizon’s soil scientists revealed hostile soil conditions for plant growth, evident erosion, and compaction.

A remediation strategy was developed to apply soil amendments, seed, and a hydromulch blanket to improve soil structure, facilitate germination, and retain moisture.

Solution

  • The remediation plan addressed the lack of microbial activity, nutrient deficiencies, and heavy compaction
  • Application of liquid calcium (AgCalcium Boost) to displace excess sodium and improve soil structure.
  • Use of fast-germinating seed in EnviroSoil for topsoil replacement.
  • Addition of major and trace elements to address deficiencies.
  • Application of a blended seed mix with EnviroLoc engineered wood fibre mulch to stabilize the batters until plant roots could secure the surface.

Equipment

Erizon utilised a fully mine-compliant HydroRig with 4×4 capability, a hydraulic cannon, and a 100m extended hose line for consistent and uniform application. Internal agitators ensured even mixing of the solution.

Scope

The project began with a 3-dimensional drone survey, followed by a detailed site and soil analysis. The remediation program was executed in two phases:

Phase 1

  • Application of EnviroSoil combined with trace elements and liquid calcium to improve soil structure.

Phase 2

  • Application of a blended seed mix with EnviroLoc to stabilize the batters.
  • Blended Seed Mix
  • A fast-acting dryland cover crop blend was used along with native Wallaby and Rhodes Grass.

The cover crop established quickly, while Wallaby and Rhodes Grass provided long-term resilience with deeper root structures.

Challenges

The project faced a narrow 5-day access window, limiting the use of the HydroRig cannon. The extended hose method was employed, requiring precise time management and skilled navigation of steep and loose access tracks by the team.

Results

Post-application, client feedback from Lycopodium was positive, noting excellent coverage, time management, and overall team collaboration. Initial signs of vegetation growth were visible within a month, with significant crop coverage and reduced erosion risks observed a few months later.

Project photos

Project Videos

Similar projects

KatCom

Curragh Mine Drain Revegetation

At Queensland’s Curragh Coal Mine, Erizon was engaged by KatCom to restore more than 80,000 m² of disturbed land, stabilising the mine drain and
Advance Bricks & Pavers

Quarry Rehabilitation

Rehabilitation of a former quarry site challenged by highly compacted clay soils and limited topsoil, with the goal of restoring the area to a
hyromulching bfm
Whittens Group

Hydromulching Project for EnergyConnect

Delivery of a tailored hydromulching solution that stabilised exposed earthworks while promoting rapid revegetation on the EnergyConnect project site.
Brimbank Council

Sunshine Energy Park Revegetation

Revegetation of a former basalt quarry and capped landfill, by establishing a robust cover of low-maintenance grasses to stabilise the landfill cap and prevent
McMahon Services

Fort Largs Temporary Dust Suppresion

Erizon was engaged to deliver a temporary dust suppression solution for a new residential development at Fort Largs in Adelaide, where exposed sandy soils
V/Line

Merbein Railway Cutting Erosion Control

V/Line engaged Erizon to stabilise the Merbein railway cutting in north‑west Victoria after severe wind and water erosion caused drainage blockages, track instability, and
Secret Link

Get in touch

For further information on how Erizon can assist you with your next Revegetation, Dust Suppression or Erosion Control project please call our team directly or complete the form below.

 

Please note we do not service Residential Projects.